Skyscrapers and stadiums tend to grab the headlines, but they’re not where the biggest construction dollars are going right now. Some of the largest projects underway in the U.S. are reservoirs, flood-control systems, contaminated-river cleanups, drinking-water facilities and ecosystem-restoration efforts — work that rarely makes the front page but reshapes entire regions.

Federal agencies, cities, utilities, engineering firms and environmental contractors are leading these efforts, and the price tags often run into the billions. Many of these projects blend heavy civil construction with environmental remediation, water management, engineering, regulatory compliance and long-term monitoring, which means they can take years — sometimes decades — from first shovel to completion.

We compiled the data below after years of hands-on work in these fields, and we wanted one place to see how the ten stack up. A quick note on the numbers: they’re not a strict apples-to-apples comparison. Some published costs are full project budgets, others are selected-remedy estimates, and Hanford’s figure reflects a remaining lifecycle cleanup estimate. We’ve flagged that distinction in the table below so you can compare responsibly.

At a Glance

ProjectStateCategoryPublished CostCost BasisStatusTarget
Hanford Site Environmental CleanupWashingtonMajor Remediation$353.6B baseline / $578.6B high range2025 remaining lifecycle cleanup estimateActiveMulti-decade
Everglades Agricultural Area ReservoirFloridaRestoration & Protection$3.9BCEPP EAA phase estimateActive construction2029
Fargo-Moorhead Area DiversionNorth Dakota / MinnesotaFlood & Coastal Resilience$3.2BOverall project budgetNear completionOperational 2027
Bull Run Filtration ProjectOregonWater Infrastructure$2.46BCurrent filtration project fundingActive construction2029
Gowanus Canal Superfund CleanupNew YorkMajor Remediation$2B+Overall cleanup plan estimateActive cleanup / CSO workMulti-year
East Side Coastal ResiliencyNew YorkFlood & Coastal Resilience$1.45BFully funded project budgetActive construction2027
Lower Passaic River / Diamond Alkali CleanupNew JerseyMajor Remediation$1.38BSelected remedy estimateEngineering / enabling workMulti-year
Brandon Road Interbasin ProjectIllinoisRestoration & Protection$1.15BOverall project estimateConstructionMulti-phase
Portland Harbor Superfund CleanupOregonMajor Remediation$1.05BSelected remedy estimateRemedial designMajor action est. 2027-28
Lower Duwamish Waterway CleanupWashingtonMajor Remediation$668M2026 settlement / cleanup valueActive cleanup10+ years

Category 01

Major Environmental Remediation

01 / 10
Waste treatment facility with tall steel structures and storage tanks at the Hanford Site in Washington state

Photo: U.S. Department of Energy

Washington

Hanford Site Environmental Cleanup

Published Cost$353.6B–$578.6B
StatusActive
Completion TargetMulti-decade

Hanford is in a category of its own. The 580-square-mile former plutonium-production complex remains one of the largest and most technically difficult environmental cleanups in the world. DOE’s 2025 lifecycle planning places the remaining baseline cleanup cost at about $353.6 billion, with a high-range estimate of $578.6 billion. Work spans radioactive tank waste, contaminated groundwater, aging facilities, waste treatment and long-term site stewardship.

Why it matters: The scale is not just financial. Hanford’s cleanup mission is expected to continue for decades, making it a rare example of a project where environmental remediation, industrial decommissioning, engineering, construction and long-term operations all overlap.

02 / 10
Excavator mounted on a barge dredging contaminated sediment from the Gowanus Canal in Brooklyn, New York

Photo: U.S. EPA

New York

Gowanus Canal Superfund Cleanup

Published Cost$2B+
StatusActive cleanup / CSO work
Completion TargetMulti-year

Brooklyn’s Gowanus Canal is one of the country’s most complex urban Superfund cleanups. EPA’s current estimate for the overall cleanup plan exceeds $2 billion, including in-canal remediation and major combined-sewer-overflow controls. The remedy includes dredging contaminated sediment, stabilizing deeper contamination, installing engineered caps and building infrastructure intended to reduce future recontamination.

Why it matters: The canal shows how remediation can become a major infrastructure program in its own right: marine construction, environmental controls and municipal wastewater upgrades are all happening in the same dense urban corridor.

03 / 10
Map of the Lower Passaic River Superfund site showing the Diamond Alkali / 80-120 Lister Avenue facility area in Newark, New Jersey

Map: Diamond Alkali Co., Newark, NJ

New Jersey

Lower Passaic River / Diamond Alkali Cleanup

Published Cost$1.38B
StatusEngineering / enabling work
Completion TargetMulti-year

EPA’s selected remedy for the lower 8.3 miles of the Passaic River calls for removing about 3.5 million cubic yards of contaminated sediment, followed by bank-to-bank capping. The selected remedy was estimated at $1.38 billion. The project is moving through engineering and enabling work required before full-scale dredging can proceed.

Why it matters: Once major field construction accelerates, this will be one of the largest contaminated-sediment cleanup efforts in the country.

04 / 10
Map of the Portland Harbor Superfund site along the Willamette River in Oregon, showing the boundaries of the contaminated area

Map: Port of Portland

Oregon

Portland Harbor Superfund Cleanup

Published Cost$1.05B
StatusRemedial design
Completion TargetMajor action est. 2027-28

The Portland Harbor Superfund remedy covers roughly 10 miles of the Lower Willamette River. EPA’s selected remedy, estimated at about $1.05 billion, uses dredging, capping, enhanced natural recovery and monitored natural recovery across hundreds of acres of contaminated sediment and riverbank.

Why it matters: The project is especially important to watch now because multiple project areas are moving through remedial design, with major remedial action currently estimated to begin in late 2027 or early 2028.

05 / 10
Excavator on a barge removing contaminated sediment from the Lower Duwamish Waterway in Seattle, Washington

Photo: King County

Washington

Lower Duwamish Waterway Cleanup

Published Cost$668M
StatusActive cleanup
Completion Target10+ years

In March 2026, EPA, the Department of Justice and Washington state announced a settlement valued at about $668 million for continued cleanup of the Lower Duwamish Waterway in Seattle. The work addresses roughly 177 acres through dredging, capping and other measures, and EPA expects the cleanup to take at least 10 years.

Why it matters: This is not a future-only project. In-water construction began in 2024, making the Duwamish a current example of long-duration remediation inside a major industrial corridor.

Category 02

Flood & Coastal Resilience

06 / 10
Aerial view of excavation equipment working on the stormwater diversion channel near Fargo, North Dakota

Photo: Metro Flood Diversion Authority

North Dakota / Minnesota

Fargo-Moorhead Area Diversion

Published Cost$3.2B
StatusNear completion
Completion TargetOperational 2027

The Fargo-Moorhead Area Diversion is a roughly $3.2 billion regional flood-protection system centered on a 30-mile stormwater diversion channel, a 22-mile southern embankment, control structures, bridges and aqueducts. It is designed to protect nearly 260,000 people and about 70 square miles of infrastructure from severe Red River flooding.

Why it matters: By late summer 2026, all 19 channel crossings had reached completion and the Sheyenne River was flowing through its new aqueduct. The system is expected to become operational in 2027.

07 / 10
New concrete floodwall under construction along the East River in Manhattan, part of New York's coastal resiliency project

Photo: NYC Department of Design and Construction

New York

East Side Coastal Resiliency

Published Cost$1.45B
StatusActive construction
Completion Target2027

New York City’s $1.45 billion East Side Coastal Resiliency project is creating a continuous flood-protection system along Manhattan’s Lower East Side using raised parkland, floodwalls, berms, movable flood gates and drainage improvements. The city says the project will protect more than 110,000 residents.

Why it matters: ESCR is notable because the flood-defense system is being integrated directly into parks, streets, utilities and public waterfront space rather than built as a stand-alone barrier.

Category 03

Environmental Restoration & Protection

08 / 10
Aerial view of wetlands and reservoir construction connecting Lake Okeechobee to the Everglades in Florida

Photo: U.S. Army Corps of Engineers, Jacksonville District / Brigida Sanchez

Florida

Everglades Agricultural Area Reservoir

Published Cost$3.9B
StatusActive construction
Completion Target2029

South of Lake Okeechobee, the Everglades Agricultural Area Reservoir is a centerpiece of the Central Everglades Planning Project. The CEPP EAA phase is estimated at $3.9 billion and includes a massive reservoir, stormwater treatment and conveyance infrastructure designed to store, clean and move more water south through the Everglades system.

Why it matters: The reservoir will cover more than 10,000 acres and hold about 240,000 acre-feet of water. In 2026, USACE announced an accelerated construction target of 2029.

09 / 10
Dewatered lock chamber showing structural steel work at the Brandon Road Lock and Dam in Illinois

Photo: U.S. Army Corps of Engineers, Rock Island District / Frances Candelaria

Illinois

Brandon Road Interbasin Project

Published Cost$1.15B
StatusConstruction
Completion TargetMulti-phase

The $1.15 billion Brandon Road Interbasin Project near Joliet is being built to reduce the risk of invasive carp and other aquatic nuisance species moving from the Illinois Waterway into the Great Lakes. The project uses layered deterrent technologies and major modifications around the Brandon Road Lock and Dam approach channel.

Why it matters: USACE moved the project into construction after the 2024 partnership agreement, and in 2026 awarded a $113.8 million contract to complete the remainder of Increment I, along with a major engineering-services contract supporting later phases.

Category 04

Critical Water Infrastructure

10 / 10
Aerial view of the Bull Run water filtration facility under construction in Oregon, with a tower crane and concrete structure

Photo: Portland Water Bureau

Oregon

Bull Run Filtration Project

Published Cost$2.46B
StatusActive construction
Completion Target2029

Portland’s Bull Run Filtration Project is a $2.46 billion drinking-water project that includes a new filtration facility and resilient pipelines connecting it to the city’s water system. The project is intended to meet drinking-water treatment requirements while strengthening resilience to wildfire, earthquakes and other disruptions.

Why it matters: Portland’s current schedule targets filtered water delivery in 2029. The project is one of the largest municipal water-treatment investments underway in the country.

What These Projects Have in Common

At first glance, a nuclear cleanup site, an Everglades reservoir, a Brooklyn Superfund canal and a North Dakota flood diversion may not seem to belong in the same story. Operationally, they do.

These are long-duration programs involving public owners, regulators, engineers, construction firms, environmental specialists, subcontractors and suppliers. They require years of procurement, reporting, documentation, field coordination and contract management — often across multiple work packages and project phases.

That creates an important second story: how prime contractors and project teams use small-business participation requirements and subcontracting goals as part of major public work. Those requirements vary by agency, funding source, certification and contract, but on projects of this size the dollars can be significant. We will examine that side of the market in a follow-up article on making SBE participation spend deliver real project value.

About Nimble Managed Services

Nimble is your proven reliable, government certified, small business set-aside (SBSA) partner. Acting as an extension of your team, Nimble provides high-level reporting and consulting solutions. We are your single source for construction managed services for: Construction Equipment, Site Services, Advanced Technologies.

Certifications:
WOSB | EDWOSB | HUBZone | SDB | DBE (All 50 States) | SBE (All 50 States) | WBE | SB (CA) | SEED (SMUD)

Research Sources

  1. Hanford Site lifecycle estimate — Hanford Advisory Board, Feb. 19, 2026. Source
  2. Everglades EAA cost and scale — U.S. Army Corps of Engineers, Aug. 2025. Source
  3. Everglades EAA 2029 target — U.S. Army Corps of Engineers, Apr. 13, 2026. Source
  4. Fargo-Moorhead cost — Metro Flood Diversion Authority, May 1, 2026. Source
  5. Fargo-Moorhead construction status — Metro Flood Diversion Authority, Sept. 7, 2026. Source
  6. Bull Run cost — Portland Water Bureau, current 2026 project page. Source
  7. Gowanus cleanup estimate — U.S. EPA, July 1, 2024 update. Source
  8. East Side Coastal Resiliency cost — City of New York, current FAQ. Source
  9. East Side Coastal Resiliency 2027 target — NYC Mayor’s Office, July 2026. Source
  10. Lower Passaic selected remedy — U.S. EPA. Source
  11. Brandon Road cost and status — U.S. Army Corps of Engineers, Apr. 13, 2026. Source
  12. Portland Harbor selected remedy — U.S. EPA, current site profile. Source
  13. Portland Harbor schedule — U.S. EPA, current site schedule. Source
  14. Lower Duwamish settlement — U.S. EPA, Mar. 4, 2026. Source